Ramada Nusa Dua Construction Progress – Оctober 2026
Here's the latest update from the Ramada Nusa Dua by Wyndham construction site.
- Bali
- TEUS Project Team
- 1 min read
In October, active preparation of the project's infrastructure continues on site in preparation for the start of the main construction works.
Current status:
— Construction of the second permanent site camp and site preparation are underway.
— Water and electricity connections are being carried out.
— Construction of the mock-up unit continues — a demonstration sample used to test the project's design and technical solutions.
Next steps:
— In December, the on-site concrete and mortar mixing plant is scheduled to be commissioned.
— The delivery of key construction materials will begin: gravel, sand, reinforcement, and formwork.
— At the end of December, provided that works proceed on schedule, foundation works are planned to begin.
We'll share new progress from the site in the next update.