DESIRE Antalya is gaining momentum every day! We share news from the construction site.
Block A1: monolithic beams and floors of the 4th floor are completed. Frames for columns, pylons, and the 5th-floor elevator shaft are ready.
Block A2-1: the 3rd floor has been completed. Columns, pylons, and elevator shaft of the 4th floor have been cast. The formwork and reinforcement of the 4th-floor slab have been completed.
Block A2-2: The columns, pylons, elevator shaft, as well as the beams and slabs of the 4th floor, have been cast.
Block A3: The columns, pylons, and elevator shaft of the 4th floor have been cast. The formwork installation for the beams and slab of the 4th floor has been completed.